Tunneling techniques

print Print
Please select which sections you would like to print:
verifiedCite
While every effort has been made to follow citation style rules, there may be some discrepancies. Please refer to the appropriate style manual or other sources if you have any questions.
Select Citation Style
Share
Share to social media
URL
https://www.britannica.com/technology/tunnel
Feedback
Corrections? Updates? Omissions? Let us know if you have suggestions to improve this article (requires login).
Thank you for your feedback

Our editors will review what you’ve submitted and determine whether to revise the article.

External Websites
Britannica Websites
Articles from Britannica Encyclopedias for elementary and high school students.

Basic tunneling system

Tunnels are generally grouped in four broad categories, depending on the material through which they pass: soft ground, consisting of soil and very weak rock; hard rock; soft rock, such as shale, chalk, and friable sandstone; and subaqueous. While these four broad types of ground condition require very different methods of excavation and ground support, nearly all tunneling operations nevertheless involve certain basic procedures: investigation, excavation and materials transport, ground support, and environmental control. Similarly, tunnels for mining and for civil-engineering projects share the basic procedures but differ greatly in the design approach toward permanence, owing to their differing purposes. Many mining tunnels have been planned only for minimum-cost temporary use during ore extraction, although the growing desire of surface owners for legal protection against subsequent tunnel collapse may cause this to change. By contrast, most civil-engineering or public-works tunnels involve continued human occupancy plus full protection of adjacent owners and are much more conservatively designed for permanent safety. In all tunnels, geologic conditions play the dominant role in governing the acceptability of construction methods and the practicality of different designs. Indeed, tunneling history is filled with instances in which a sudden encounter with unanticipated conditions caused long stoppages for changes in construction methods, in design, or in both, with resulting great increases in cost and time. At the Awali Tunnel in Lebanon in 1960, for example, a huge flow of water and sand filled over 2 miles of the bore and more than doubled construction time to eight years for its 10-mile length.

Geologic investigation

Thorough geologic analysis is essential in order to assess the relative risks of different locations and to reduce the uncertainties of ground and water conditions at the location chosen. In addition to soil and rock types, key factors include the initial defects controlling behaviour of the rock mass; size of rock block between joints; weak beds and zones, including faults, shear zones, and altered areas weakened by weathering or thermal action; groundwater, including flow pattern and pressure; plus several special hazards, such as heat, gas, and earthquake risk. For mountain regions the large cost and long time required for deep borings generally limit their number; but much can be learned from thorough aerial and surface surveys, plus well-logging and geophysical techniques developed in the oil industry. Often the problem is approached with flexibility toward changes in design and in construction methods and with continuous exploration ahead of the tunnel face, done in older tunnels by mining a pilot bore ahead and now by drilling. Japanese engineers have pioneered methods for prelocating troublesome rock and water conditions.

For large rock chambers and also particularly large tunnels, the problems increase so rapidly with increasing opening size that adverse geology can make the project impractical or at least tremendously costly. Hence, the concentrated opening areas of these projects are invariably investigated during the design stage by a series of small exploratory tunnels called drifts, which also provide for in-place field tests to investigate engineering properties of the rock mass and can often be located so their later enlargement affords access for construction.

Since shallow tunnels are more often in soft ground, borings become more practical. Hence, most subways involve borings at intervals of 100–500 feet to observe the water table and to obtain undisturbed samples for testing strength, permeability, and other engineering properties of the soil. Portals of rock tunnels are often in soil or in rock weakened by weathering. Being shallow, they are readily investigated by borings, but, unfortunately, portal problems have frequently been treated lightly. Often they are only marginally explored or the design is left to the contractor, with the result that a high percentage of tunnels, especially in the United States, have experienced portal failures. Failure to locate buried valleys has also caused a number of costly surprises. The five-mile Oso Tunnel in New Mexico offers one example. There, in 1967, a mole had begun to progress well in hard shale, until 1,000 feet from the portal it hit a buried valley filled with water-bearing sand and gravel, which buried the mole. After six months’ delay for hand mining, the mole was repaired and soon set new world records for advance rate—averaging 240 feet per day with a maximum of 420 feet per day.

Excavation and materials handling

Excavation of the ground within the tunnel bore may be either semicontinuous, as by handheld power tools or mining machine, or cyclic, as by drilling and blasting methods for harder rock. Here each cycle involves drilling, loading explosive, blasting, ventilating fumes, and excavation of the blasted rock (called mucking). Commonly, the mucker is a type of front-end loader that moves the broken rock onto a belt conveyor that dumps it into a hauling system of cars or trucks. As all operations are concentrated at the heading, congestion is chronic, and much ingenuity has gone into designing equipment able to work in a small space. Since progress depends on the rate of heading advance, it is often facilitated by mining several headings simultaneously, as opening up intermediate headings from shafts or from adits driven to provide extra points of access for longer tunnels.

For smaller diameters and longer tunnels, a narrow-gauge railroad is commonly employed to take out the muck and bring in workers and construction material. For larger-size bores of short to moderate length, trucks are generally preferred. For underground use these require diesel engines with scrubbers to eliminate dangerous gases from the exhaust. While existing truck and rail systems are adequate for tunnels progressing in the range of 40–60 feet (12–18 metres) per day, their capacity is inadequate to keep up with fast-moving moles progressing at the rate of several hundred feet per day. Hence, considerable attention is being devoted to developing high-capacity transport systems—continuous-belt conveyors, pipelines, and innovative rail systems (high-capacity cars on high-speed trains). Muck disposal and its transport on the surface can also be a problem in congested urban areas. One solution successfully applied in Japan is to convey it by pipeline to sites where it can be used for reclamation by landfill.

For survey control, high-accuracy transit-level work (from base lines established by mountaintop triangulation) has generally been adequate; long tunnels from opposite sides of the mountain commonly meet with an error of one foot or less. Further improvements are likely from the recent introduction of the laser, the pencil-size light beam of which supplies a reference line readily interpreted by workers. Most moles in the United States now use a laser beam to guide steering, and some experimental machines employ electronic steering actuated by the laser beam.

Ground support

The dominant factor in all phases of the tunneling system is the extent of support needed to hold the surrounding ground safely. Engineers must consider the type of support, its strength, and how soon it must be installed after excavation. The key factor in timing support installation is so-called stand-up time—i.e., how long the ground will safely stand by itself at the heading, thus providing a period for installing supports. In soft ground, stand-up time can vary from seconds in such soils as loose sand up to hours in such ground as cohesive clay and even drops to zero in flowing ground below the water table, where inward seepage moves loose sand into the tunnel. Stand-up time in rock may vary from minutes in raveling ground (closely fractured rock where pieces gradually loosen and fall) up to days in moderately jointed rock (joint spacing in feet) and may even be measured in centuries in nearly intact rock, where the rock-block size (between joints) equals or exceeds size of the tunnel opening, thus requiring no support. While a miner generally prefers rock to soft ground, local occurrences of major defects within the rock can effectively produce a soft-ground situation; passage through such areas generally requires radical change to the use of a soft-ground type of support.

Under most conditions, tunneling causes a transfer of the ground load by arching to sides of the opening, termed the ground-arch effect. At the heading the effect is three-dimensional, locally creating a ground dome in which the load is arched not only to the sides but also forward and back. If permanence of the ground arch is completely assured, stand-up time is infinite, and no support is required. Ground-arch strength usually deteriorates with time, however, increasing the load on the support. Thus, the total load is shared between support and ground arch in proportion to their relative stiffness by a physical mechanism termed structure-medium interaction. The support load increases greatly when the inherent ground strength is much reduced by allowing excessive yield to loosen the rock mass. Because this may occur when installation of support is delayed too long, or because it may result from blast damage, good practice is based on the need to preserve the strength of the ground arch as the strongest load-carrying member of the system, by prompt installation of proper support and by preventing blast damage and movement from water inflow that has a tendency to loosen the ground.

Because stand-up time drops rapidly as size of the opening increases, the full-face method of advance, in which the entire diameter of the tunnel is excavated at one time, it is most suitable for strong ground or for smaller tunnels. The effect of weak ground can be offset by decreasing the size of opening initially mined and supported, as in the top heading and bench method of advance. For the extreme case of very soft ground, this approach results in the multiple-drift method of advance, in which the individual drifts are reduced to a small size that is safe for excavation and portions of the support are placed in each drift and progressively connected as the drifts are expanded. The central core is left unexcavated until sides and crown are safely supported, thus providing a convenient central buttress for bracing the temporary support in each individual drift. While this obviously slow multidrift method is an old technique for very weak ground, such conditions still force its adoption as a last resort in some modern tunnels. In 1971, for example, on the Straight Creek interstate highway tunnel in Colorado, a very complex pattern of multiple drifts was found necessary to advance this large horseshoe-shaped tunnel 42 by 45 feet high through a weak shear zone more than 1,000 feet wide, after unsuccessful trials with full-face operation of a shield.

In early tunnels, timber was used for the initial or temporary support, followed by a permanent lining of brick or stone masonry. Since steel became available, it has been widely used as the first temporary stage or primary support. For protection against corrosion, it is nearly always encased in concrete as a second stage or final lining. Steel-rib support with timber blocking outside has been widely employed in rock tunnels. The horseshoe shape is common for all but the weakest rocks, since the flat bottom facilitates hauling. By contrast, the stronger and more structurally efficient circular shape is generally required to support the greater loads from soft ground. Newer types of supports are discussed below with more modern tunnel procedures, in which the trend is away from two stages of support toward a single support system, part installed early and gradually strengthened in increments for conversion to the final complete support system.

Environmental control

In all but the shortest tunnels, control of the environment is essential to provide safe working conditions. Ventilation is vital, both to provide fresh air and to remove explosive gases such as methane and noxious gases, including blast fumes. While the problem is reduced by using diesel engines with exhaust scrubbers and by selecting only low-fume explosives for underground use, long tunnels involve a major ventilating plant that employs a forced draft through lightweight pipes up to three feet in diameter and with booster fans at intervals. In smaller tunnels, the fans are frequently reversible, exhausting fumes immediately after blasting, then reversing to supply fresh air to the heading where the work is now concentrated.

High-level noise generated at the heading by drilling equipment and throughout the tunnel by high-velocity air in the vent lines frequently requires the use of earplugs with sign language for communication. In the future, equipment operators may work in sealed cabs, but communication is an unsolved problem. Electronic equipment in tunnels is prohibited, since stray currents may activate blasting circuits. Thunderstorms may also produce stray currents and require special precautions.

Dust is controlled by water sprays, wet drilling, and the use of respirator masks. Since prolonged exposure to dust from rocks containing a high percentage of silica may cause a respiratory ailment known as silicosis, severe conditions require special precautions, such as a vacuum-exhaust hood for each drill.

While excess heat is more common in deep tunnels, it occasionally occurs in fairly shallow tunnels. In 1953, workers in the 6.4-mile Telecote Tunnel near Santa Barbara, California, were transported immersed in water-filled mine cars through the hot area (117° F [47° C]). In 1970 a complete refrigeration plant was required to progress through a huge inflow of hot water at 150° F (66° C) in the 7-mile Graton Tunnel, driven under the Andes to drain a copper mine in Peru.

Modern soft-ground tunneling

Settlement damage and lost ground

Soft-ground tunnels most commonly are used for urban services (subways, sewers, and other utilities) for which the need for quick access by passengers or maintenance staff favours a shallow depth. In many cities this means that the tunnels are above bedrock, making tunneling easier but requiring continuous support. The tunnel structure in such cases is generally designed to support the entire load of the ground above it, in part because the ground arch in soil deteriorates with time and in part as an allowance for load changes resulting from future construction of buildings or tunnels. Soft-ground tunnels are typically circular in shape because of this shape’s inherently greater strength and ability to readjust to future load changes. In locations within street rights-of-way, the dominant concern in urban tunneling is the need to avoid intolerable settlement damage to adjoining buildings. While this is rarely a problem in the case of modern skyscrapers, which usually have foundations extending to rock and deep basements often extending below the tunnel, it can be a decisive consideration in the presence of moderate-height buildings, whose foundations are usually shallow. In this case the tunnel engineer must choose between underpinning or employing a tunneling method that is sufficiently foolproof that it will prevent settlement damage.

Surface settlement results from lost ground—i.e., ground that moves into the tunnel in excess of the tunnel’s actual volume. All soft-ground tunneling methods result in a certain amount of lost ground. Some is inevitable, such as the slow lateral squeeze of plastic clay that occurs ahead of the tunnel face as new stresses from doming at the heading cause the clay to move toward the face before the tunnel even reaches its location. Most lost ground, however, results from improper construction methods and careless workmanship. Hence the following emphasizes reasonably conservative tunneling methods, which offer the best chance for holding lost ground to an acceptable level of approximately 1 percent.

Hand-mined tunnels

The ancient practice of hand mining is still economical for some conditions (shorter and smaller tunnels) and may illustrate particular techniques better than its mechanized counterpart. Examples are forepoling and breasting techniques as developed for the hazardous case of running (unstable) ground. Figure 1 shows the essentials of the process: heading advanced under a roof of forepole planks that are driven ahead at the crown (and at the sides in severe cases) plus continuous planking or breasting at the heading. With careful work the method permits advance with very little lost ground. The top breastboard may be removed, a small advance excavated, this breastboard replaced, and progress continued by working down one board at a time. While solid wall forepoling is nearly a lost art, an adaptation of it is termed spiling. In spiling the forepoles are intermittent with gaps between. Crown spiling is still resorted to for passing bad ground; in this case spiles may consist of rails driven ahead, or even steel bars set in holes drilled into crushed rock.

In ground providing a reasonable stand-up time, a modern support system uses steel liner-plate sections placed against the soil and bolted into a solid sheeted complete circle and, in larger tunnels, strengthened inside by circular steel ribs. Individual liner plates are light in weight and are easily erected by hand. By employing small drifts (horizontal passageways), braced to a central core, liner-plate technique has been successful in larger tunnels—Figure 2 shows 1940 practice on the 20-foot tunnels of the Chicago subway. The top heading is carried ahead, preceded slightly by a “monkey drift” in which the wall plate is set and serves as a footing for the arch ribs, also to span over as the wall plate is underpinned by erecting posts in small notches at each side of the lower bench. As the ribs and liner plate provide only a light support, they are stiffened by installation of a concrete lining about one day behind the mining. While liner-plate tunnels are more economical than shield tunnels, the risks of lost ground are somewhat greater and require not only very careful workmanship but also thorough soil-mechanics investigation in advance, pioneered in Chicago by Karl V. Terzaghi.

Shield tunnels

The risk of lost ground can also be reduced by using a shield with individual pockets from which workers can mine ahead; these can quickly be closed to stop a run-in. In extremely soft ground the shield may be simply shoved ahead with all its pockets closed, completely displacing the soil ahead of it; or it may be shoved with some of the pockets open, through which the soft soil extrudes like a sausage, cut into chunks for removal by a belt conveyor. The first of these methods was used on the Lincoln Tunnel in Hudson River silt.

Support erected inside the tail of the shield consists of large segments, so heavy that they require a power erector arm for positioning while being bolted together. Because of its high resistance to corrosion, cast iron has been the most commonly used material for segments, thus eliminating the need for a secondary lining of concrete. Today, lighter segments are employed. In 1968, for example, the San Francisco subway used welded steel-plate segments, protected outside by a bituminous coating and galvanized inside. British engineers have developed precast concrete segments that are proving popular in Europe.

An inherent problem with the shield method is the existence of a 2- to 5-inch (5- to 13-centimetre) ring-shaped void left outside the segments as the result of the thickness of the skin plate and the clearance needed for segment erection. Movement of soil into this void could result in up to 5 percent lost ground, an amount intolerable in urban work. Lost ground is held to reasonable levels by promptly blowing small-sized gravel into the void, then injecting cement grout (sand-cement-water mixture).

Water control

A soft-ground tunnel below the water table involves a constant risk of a run-in—i.e., soil and water flowing into the tunnel, which often results in complete loss of the heading. One solution is to lower the water table below the tunnel bottom before construction begins. This can be accomplished by pumping from deep wells ahead and from well points within the tunnel. While this benefits the tunneling, dropping the water table increases the loading on deeper soil layers. If these are relatively compressible, the result can be a major settlement of adjacent buildings on shallow foundations, an extreme example being a 15- to 20-foot subsidence in Mexico City due to overpumping.

When soil conditions make it undesirable to drop the water table, compressed air inside the tunnel may offset the outside water pressure. In larger tunnels, air pressure is generally set to balance the water pressure in the lower part of the tunnel, with the result that it then exceeds the smaller water pressure at the crown (upper part). Since air tends to escape through the upper part of the tunnel, constant inspection and repair of leaks with straw and mud are required. Otherwise, a blowout could occur, depressurizing the tunnel and possibly losing the heading as soil enters. Compressed air greatly increases operating costs, partly because a large compressor plant is needed, with standby equipment to insure against loss of pressure and partly because of the slow movement of workers and muck trains through the air locks. The dominant factor, however, is the huge reduction in productive time and lengthy decompression time required for people working under air to prevent the crippling disease known as the bends (or caisson disease), also encountered by divers. Regulations stiffen as pressure increases up to the usual maximum of 45 pounds per square inch (3 atmospheres) where daily time is limited to one hour working and six hours for decompression. This, plus higher hazard pay, makes tunneling under high air pressure very costly. In consequence, many tunneling operations attempt to lower the operating air pressure, either by partially dropping the water table or, especially in Europe, by strengthening the ground through the injection of solidifying chemical grouts. French and British grouting-specialist companies have developed a number of highly engineered chemical grouts, and these are achieving considerable success in advance cementing of weak soil.

Soft-ground moles

Since their first success in 1954, moles (mining machines) have been rapidly adopted worldwide. Close copies of the Oahe moles were used for similar large-diameter tunnels in clay shale at Gardiner Dam in Canada and at Mangla Dam in Pakistan during the mid-1960s, and subsequent moles have succeeded at many other locations involving tunneling through soft rocks. Of the several hundred moles built, most have been designed for the more easily excavated soil tunnel and are now beginning to divide into four broad types (all are similar in that they excavate the earth with drag teeth and discharge the muck onto a belt conveyor, and most operate inside a shield).

The open-face-wheel type is probably the most common. In the wheel the cutter arm rotates in one direction; in a variant model it oscillates back and forth in a windshield-wiper action that is most suitable in wet, sticky ground. While suitable for firm ground, the open-face mole has sometimes been buried by running or loose ground.

The closed-faced-wheel mole partly offsets this problem, since it can be kept pressed against the face while taking in muck through slots. Since the cutters are changed from the face, changing must be done in firm ground. This kind of mole performed well, beginning in the late 1960s, on the San Francisco subway project in soft to medium clay with some sand layers, averaging 30 feet per day. In this project, mole operation made it cheaper and safer to drive two single-track tunnels than one large double-track tunnel. When adjacent buildings had deep foundations, a partial lowering of the water table permitted operations under low pressure, which succeeded in limiting surface settlement to about one inch. In areas of shallow building foundations, dewatering was not permitted; air pressure was then doubled to 28 pounds per square inch, and settlements were slightly smaller.

A third type is the pressure-on-face mole. Here, only the face is pressurized, and the tunnel proper operates in free air—thus avoiding the high costs of labour under pressure. In 1969 a first major attempt used air pressure on the face of a mole operating in sands and silts for the Paris Metro. A 1970 attempt in volcanic clays of Mexico City used a clay-water mixture as a pressurized slurry (liquid mixture); the technique was novel in that the slurry muck was removed by pipeline, a procedure simultaneously also used in Japan with a 23-foot-diameter pressure-on-face mole. The concept has been further developed in England, where an experimental mole of this type was first constructed in 1971.

The digger-shield type of machine is essentially a hydraulic-powered digger arm excavating ahead of a shield, whose protection can be extended forward by hydraulically operated poling plates, acting as retractable spiles. In 1967–70 in the 26-foot-diameter Saugus-Castaic Tunnel near Los Angeles, a mole of this type produced daily progress in clayey sandstone averaging 113 feet per day and 202 feet maximum, completing five miles of tunnel one-half year ahead of schedule. In 1968 an independently developed device of similar design also worked well in compacted silt for a 12-foot-diameter sewer tunnel in Seattle.

Pipe jacking

For small tunnels in a five- to eight-foot size range, small moles of the open-face-wheel type have been effectively combined with an older technique known as pipe jacking, in which a final lining of precast concrete pipe is jacked forward in sections. The system used in 1969 on two miles of sewer in Chicago clay had jacking runs up to 1,400 feet between shafts. A laser-aligned wheel mole cut a bore slightly larger than the lining pipe. Friction was reduced by bentonite lubricant added outside through holes drilled from the surface, which were later used for grouting any voids outside the pipe lining. The original pipe-jacking technique was developed particularly for crossing under railroads and highways as a means of avoiding traffic interruption from the alternate of construction in open trench. Since the Chicago project showed a potential for progress of a few hundred feet per day, the technique has become attractive for small tunnels.

Modern rock tunneling

Nature of the rock mass

It is important to distinguish between the high strength of a block of solid or intact rock and the much lower strength of the rock mass consisting of strong rock blocks separated by much weaker joints and other rock defects. While the nature of intact rock is significant in quarrying, drilling, and cutting by moles, tunneling and other areas of rock engineering are concerned with the properties of the rock mass. These properties are controlled by the spacing and nature of the defects, including joints (generally fractures caused by tension and sometimes filled with weaker material), faults (shear fractures frequently filled with claylike material called gouge), shear zones (crushed from shear displacement), altered zones (in which heat or chemical action have largely destroyed the original bond cementing the rock crystals), bedding planes, and weak seams (in shale, often altered to clay). Since these geologic details (or hazards) usually can only be generalized in advance predictions, rock-tunneling methods require flexibility for handling conditions as they are encountered. Any of these defects can convert the rock to the more hazardous soft-ground case.

Also important is the geostressi.e., the state of stress existing in situ prior to tunneling. Though conditions are fairly simple in soil, geostress in rock has a wide range because it is influenced by the stresses remaining from past geologic events: mountain building, crustal movements, or load subsequently removed (melting of glacial ice or erosion of former sediment cover). Evaluation of the geostress effects and the rock mass properties are primary objectives of the relatively new field of rock mechanics and are dealt with below with underground chambers since their significance increases with opening size. This section therefore emphasizes the usual rock tunnel, in the size range of 15 to 25 feet.

Conventional blasting

Blasting is carried on in a cycle of drilling, loading, blasting, ventilating fumes, and removing muck. Since only one of these five operations can be conducted at a time in the confined space at the heading, concentrated efforts to improve each have resulted in raising the rate of advance to a range of 40–60 feet per day, or probably near the limit for such a cyclic system. Drilling, which consumes a major part of the time cycle, has been intensely mechanized in the United States. High-speed drills with renewable bits of hard tungsten carbide are positioned by power-operated jib booms located at each platform level of the drilling jumbo (a mounted platform for carrying drills). Truck-mounted jumbos are used in larger tunnels. When rail-mounted, the drilling jumbo is arranged to straddle the mucker so that drilling can resume during the last phase of the mucking operation.

By experimenting with various drill-hole patterns and the sequence of firing explosives in the holes, Swedish engineers have been able to blast a nearly clean cylinder in each cycle, while minimizing use of explosives.

Dynamite, the usual explosive, is fired by electric blasting caps, energized from a separate firing circuit with locked switches. Cartridges are generally loaded individually and seated with a wooden tamping rod; Swedish efforts to expedite loading often employ a pneumatic cartridge loader. American efforts toward reduced loading time have tended to replace dynamite with a free-running blasting agent, such as a mixture of ammonium nitrate and fuel oil (called AN-FO), which in granular form (prills) can be blown into the drill hole by compressed air. While AN-FO-type agents are cheaper, their lower power increases the quantity required, and their fumes usually increase ventilating requirements. For wet holes, the prills must be changed to a slurry requiring special processing and pumping equipment.

Rock support

Most common loading on the support of a tunnel in hard rock is due to the weight of loosened rock below the ground arch, where designers rely particularly on experience with Alpine tunnels as evaluated by two Austrians, Karl V. Terzaghi, the founder of soil mechanics, and Josef Stini, a pioneer in engineering geology. The support load is greatly increased by factors weakening the rock mass, particularly blasting damage. Furthermore, if a delay in placing support allows the zone of rock loosening to propagate upward (i.e., rock falls from the tunnel roof), the rock-mass strength is reduced, and the ground arch is raised. Obviously, the loosened rock load can be greatly altered by a change in joint inclination (orientation of rock fractures) or by the presence of one or more of the rock defects previously mentioned. Less frequent but more severe is the case of high geostress, which in hard, brittle rock may result in dangerous rock bursts (explosive spalling off from the tunnel side) or in a more plastic rock mass may exhibit a slow squeezing into the tunnel. In extreme cases, squeezing ground has been handled by allowing the rock to yield while keeping the process under control, then remining and resetting initial support several times, plus deferring concrete lining until the ground arch becomes stabilized.

For many years steel rib sets were the usual first-stage support for rock tunnels, with close spacing of the wood blocking against the rock being important to reduce bending stress in the rib. Advantages are increased flexibility in changing rib spacing plus the ability to handle squeezing ground by resetting the ribs after remining. A disadvantage is that in many cases the system yields excessively, thus inviting weakening of the rock mass. Finally, the rib system serves only as a first-stage or temporary support, requiring a second-stage encasement in a concrete lining for corrosion protection.

Concrete lining

Concrete linings aid fluid flow by providing a smooth surface and insure against rock fragment falling on vehicles using the tunnel. While shallow tunnels are often lined by dropping concrete down holes drilled from the surface, the greater depth of most rock tunnels requires concreting entirely within the tunnel. Operations in such congested space involve special equipment, including agitator cars for transport, pumps or compressed-air devices for placing the concrete, and telescoping arch forms that can be collapsed to move forward inside forms remaining in place. The invert is generally concreted first, followed by the arch where forms must be left in place from 14 to 18 hours for the concrete to gain necessary strength. Voids at the crown are minimized by keeping the discharge pipe buried in fresh concrete. The final operation consists of contact grouting, in which a sand-cement grout is injected to fill any voids and to establish full contact between lining and ground. The method usually produces progress in the range of 40 to 120 feet per day. In the 1960s there was a trend toward an advancing-slope method of continuous concreting, as originally devised for embedding the steel cylinder of a hydropower penstock. In this procedure, several hundred feet of forms are initially set, then collapsed in short sections and moved forward after the concrete has gained necessary strength, thus keeping ahead of the continuously advancing slope of fresh concrete. As a 1968 example, Libby Dam’s Flathead Tunnel in Montana attained a concreting rate of 300 feet (90 metres) per day by using the advancing slope method.

Rock bolts

Rock bolts are used to reinforce jointed rock much as reinforcing bars supply tensile resistance in reinforced concrete. After early trials about 1920, they were developed in the 1940s for strengthening laminated roof strata in mines. For public works their use has increased rapidly since 1955, as confidence has developed from two independent pioneering applications, both in the early 1950s. One was the successful change from steel rib sets to cheaper rock bolts on major portions of the 85 miles of tunnels forming New York City’s Delaware River Aqueduct. The other was the success of such bolts as the sole rock support in large underground powerhouse chambers of Australia’s Snowy Mountains project. Since about 1960, rock bolts have had major success in providing the sole support for large tunnels and rock chambers with spans up to 100 feet. Bolts are commonly sized from 0.75 to 1.5 inches and function to create a compression across rock fissures, both to prevent the joints opening and to create resistance to sliding along the joints. For this they are placed promptly after blasting, anchored at the end, tensioned, and then grouted to resist corrosion and to prevent anchor creep. Rock tendons (prestressed cables or bundled rods, providing higher capacity than rock bolts) up to 250 feet long and prestressed to several hundred tons each have succeeded in stabilizing many sliding rock masses in rock chambers, dam abutments, and high rock slopes. A noted example is their use in reinforcing the abutments of Vaiont Dam in Italy. In 1963 this project experienced disaster when a giant landslide filled the reservoir, causing a huge wave to overtop the dam, with large loss of life. Remarkably, the 875-foot-high arch dam survived this huge overloading; the rock tendons are believed to have supplied a major strengthening.

Shotcrete

Shotcrete is small-aggregate concrete conveyed through a hose and shot from an air gun onto a backup surface on which it is built up in thin layers. Though sand mixes had been so applied for many years, new equipment in the late 1940s made it possible to improve the product by including coarse aggregate up to one inch; strengths of 6,000 to 10,000 pounds per square inch (400 to 700 kilograms per square centimetre) became common. Following initial success as rock-tunnel support in 1951–55 on the Maggia Hydro Project in Switzerland, the technique was further developed in Austria and Sweden. The remarkable ability of a thin shotcrete layer (one to three inches) to bond to and knit fissured rock into a strong arch and to stop raveling of loose pieces soon led to shotcrete largely superseding steel rib support in many European rock tunnels. By 1962 the practice had spread to South America. From this experience plus limited trial at the Hecla Mine in Idaho, the first major use of coarse-aggregate shotcrete for tunnel support in North America developed in 1967 on the Vancouver Railroad Tunnel, with a cross section 20 by 29 feet high and a length of two miles. Here an initial two- to four-inch coat proved so successful in stabilizing hard, blocky shale and in preventing raveling in friable (crumbly) conglomerate and sandstone that the shotcrete was thickened to six inches in the arch and four inches on the walls to form the permanent support, saving about 75 percent of the cost of the original steel ribs and concrete lining.

A key to shotcreting’s success is its prompt application before loosening starts to reduce the strength of the rock mass. In Swedish practice this is accomplished by applying immediately after blasting and, while mucking is in progress, utilizing the “Swedish robot,” which allows the operator to remain under the protection of the previously supported roof. On the Vancouver tunnel, shotcrete was applied from a platform extending forward from the jumbo while the mucking machine operated below. By taking advantage of several unique properties of shotcrete (flexibility, high bending strength, and ability to increase thickness by successive layers), Swedish practice has developed shotcreting into a single-support system that is strengthened progressively as needed for conversion into the final support.

Preserving rock strength

In rock tunnels, the requirements for support can be significantly decreased to the extent that the construction method can preserve the inherent strength of the rock mass. The opinion has been often expressed that a high percentage of support in rock tunnels in the United States (perhaps over half) has been needed to stabilize rock damaged by blasting rather than because of an inherently low strength of the rock. As a remedy, two techniques are currently available. First is the Swedish development of sound-wall blasting (to preserve rock strength), treated below under rock chambers, since its importance increases with size of the opening. The second is the American development of rock moles that cut a smooth surface in the tunnel, thus minimizing rock damage and support needs—here limited to rock bolts connected by steel straps for this sandstone tunnel. In stronger rocks (as the 1970 Chicago sewers in dolomite) mole excavation not only largely eliminated need for support but also produced a surface of adequate smoothness for sewer flow, which permitted a major saving by omitting the concrete lining. Since their initial success in clay shale, the use of rock moles has expanded rapidly and has achieved significant success in medium-strength rock such as sandstone, siltstone, limestone, dolomite, rhyolite, and schist. The advance rate has ranged up to 300 to 400 feet per day and has often outpaced other operations in the tunneling system. While experimental moles were used successfully to cut hard rock such as granite and quartzite, such devices were not economical, because cutter life was short, and frequent cutter replacement was costly. This was likely to change, however, as mole manufacturers sought to extend the range of application. Improvement in cutters and progress in reducing the time lost from equipment breakages were producing consistent improvements.

American moles have developed two types of cutters: disk cutters that wedge out the rock between initial grooves cut by the hard-faced rolling disks, and roller-bit cutters using bits initially developed for fast drilling of oil wells. As later entrants in the field, European manufacturers have generally tried a different approach—milling-type cutters that mill or plane away part of the rock, then shear off undercut areas. Attention is also focusing on broadening the moles’ capabilities to function as the primary machine of the whole tunneling system. Thus, future moles are expected not only to cut rock but also to explore ahead for dangerous ground; handle and treat bad ground; provide a capability for prompt erection of support, rock bolting, or shotcreting; change cutters from the rear in loose ground; and produce rock fragments of a size appropriate to capability of the muck removal system. As these problems are solved, the continuous-tunneling system by mole is expected largely to replace the cyclic drilling and blasting system.

Water inflows

Exploring ahead of the path of a tunnel is particularly necessary for location of possible high water inflows and permitting their pretreatment by drainage or grouting. When high-pressure flows occur unexpectedly, they result in long stoppages. When huge flows are encountered, one approach is to drive parallel tunnels, advancing them alternately so that one relieves pressure in front of the other. This was done in 1898 in work on the Simplon Tunnel and in 1969 on the Graton Tunnel in Peru, where flow reached 60,000 gallons (230,000 litres) per minute. Another technique is to depressurize ahead by drain holes (or small drainage drifts on each side), an extreme example being the 1968 Japanese handling of extraordinarily difficult water and rock conditions on the Rokko Railroad Tunnel, using approximately three-quarters of a mile of drainage drifts and five miles of drain holes in a one-quarter-mile length of the main tunnel.

Heavy ground

The miner’s term for very weak or high geostress ground that causes repeated failures and replacement of support is heavy ground. Ingenuity, patience, and large increases of time and funds are invariably required to deal with it. Special techniques have generally been evolved on the job, as indicated by a few of the numerous examples. On the 7.2-mile Mont Blanc Vehicular Tunnel of 32-foot size under the Alps in 1959–63, a pilot bore ahead helped greatly to reduce rock bursts by relieving the high geostress. The 5-mile, 14-foot El Colegio Penstock Tunnel in Colombia was completed in 1965 in bituminous shale, requiring the replacement and resetting of more than 2,000 rib sets, which buckled as the invert (bottom supports) and sides gradually squeezed in up to 3 feet, and by deferring concreting until the ground arch stabilized.

While the ground arch eventually stabilized in these and numerous similar examples, knowledge is inadequate to establish the point between desirable deformation (to mobilize ground strength) and excessive deformation (which reduces its strength), and improvement is most likely to come from carefully planned and observed field-test sections at prototype scale, but these have been so costly that very few have actually been executed, notably the 1940 test sections in clay on the Chicago subway and the 1950 Garrison Dam test tunnel in the clay-shale of North Dakota. Such prototype field testing has resulted, however, in substantial savings in eventual tunnel cost. For harder rock, reliable results are even more fragmentary.

Unlined tunnels

Numerous modest-size conventionally blasted tunnels have been left unlined if human occupancy was to be rare and the rock was generally good. Initially, only weak zones are lined, and marginal areas are left for later maintenance. Most common is the case of a water tunnel that is built oversized to offset the friction increase from the rough sides and, if a penstock tunnel, is equipped with a rock trap to catch loose rock pieces before they can enter the turbines. Most of these have been successful, particularly if operations could be scheduled for periodic shutdowns for maintenance repair of rockfalls; the Laramie-Poudre Irrigation Tunnel in northern Colorado experienced only two significant rockfalls in 60 years, each easily repaired during a nonirrigation period. In contrast, a progressive rockfall on the 14-mile Kemano penstock tunnel in Canada resulted in shutting down the whole town of Kitimat in British Columbia, and vacationing workers for nine months in 1961 since there were no other electric sources to operate the smelter. Thus, the choice of an unlined tunnel involves a compromise between initial saving and deferred maintenance plus evaluation of the consequences of a tunnel shutdown.